pengaruh Metode Pelaksanaan Terhadap Biaya dan percepatan Proyek bangunan gedung RUSUN TNI AD SAMARINDA
Kusnadi, S.T., M.T. (Dosen Universitas Tridharma Prodi Teknik Sipil)
Hikmah Maya Sari, S.T., M.T. (Dosen Universitas Tridharma Prodi Teknik Sipil)
Pandu Wijaya, ST. (Mahasiswa Universitas Tridharma Prodi Teknik Sipil)
Abstract
One of the objectives of flats and flats is one of the government's efforts to improve the welfare and labor productivity TNI AD and members of the police on duty throughout the territory of the Republic of Indonesia. In the implementation of the construction of flats (Rusun), especially in the Rusun TNI AD Samarinda changes the method it started using precast system was not allowed to do when the target completion 5 months, when viewed from the location and supply of concrete materials and therefore the method is combined with a conventional method. The time delay of project implementation is the responsibility of the contractor as project manager. If the delay in the long term, it could have been sanctioned by the contractor awarded the project owner as no longer relevant to the time planned in the contract documents.
With the calculations done manually, using the help of Microsoft Project is one part of Microsoft Office that can help perform calculations faster. To determine the work to be carried out calculations project acceleration with optimum cost.
Based on the analysis time and costs that have been done, it can be concluded: The proper method to accelerate project implementation time is a combination system that combines a precast system and konvensional. With the combined system can be accelerated time is 25 days. With a combined system costs is Rp. 542,110,123.93 less than conventional systems but more than precast system.